Preflex Parking Garage at the Nuremberg Exhibition Center

C + P erected a parking garage with space for 850 cars for NürnbergMesse GmbH within 12 weeks. Within 3 months 30 panel elements per week were assembled, independently of the weather conditions, making a total of 350 installed panel elements. Structural and civil engineering took place in parallel.

Bauherr Developer NürnbergMesse GmbH
Leistung Service Preflex® Parking Garage
Place of construction Nuremberg, Bavaria
Tonnage 450 t

CHRISTMANN + PFEIFER.

The ideal network of specialists for your building project.

PREFLEX® Parking Garage.

This modular parking system creates additional parking space in no time at all – regardless of whether its 10, 100 or 1,000 parking spaces. Realizable in the form of a purchase, rental or lease model!

Read more

PREFLEX® Girder.

Thanks to its special design, the Preflex® girder represents a high performance and intelligent solution for bridge building where small and medium spans are involved.

Read more

Structural Steelwork Production.

At three production sites in Germany, we process up to 30,000 t of steel every year. This guarantees high quality as well as adherence to costs and deadlines.

Read more