New production hall near Regensburg

When standing in front of the new production hall of the Hieber company in Barbing today, you hardly suspect: behind the aerated concrete facade hides a heart of steel.

We supplied and assembled 572 tons of coated steel structure from our production after our own technical processing for the sheet metal and metal processing company near Regensburg. 93 tons were accounted for by the crane runway girders alone.

In addition, we also took on the installation of the 9,447 square meters of trapezoidal roof sheeting, including thermal insulation and sealing, as well as the installation of the 8 skylight strips, each almost 20 meters long, with smoke and heat extraction systems. Among other things, the support of a crane runway on the on-site racking system proved to be challenging.

Bauherr Developer Hieber GmbH
Leistung Service Structural Steelwork
Tonnage 572 t
Place of construction Barbing, Bavaria

CHRISTMANN + PFEIFER.

The ideal network of specialists for your building project.

Structural Steelwork.

Due to its sustainable characteristics, flexibility of use and economic efficiency, we rely on steel as the ideal material for industrial buildings.

Read more

Structural Steelwork Production.

Thanks to our own production sites in Germany, we can flexibly handle production capacities at any time and implement projects with pinpoint accuracy.

Read more

Engineering.

We offer integral planning of the complete scope of work and for all work phases from a single source. Our optimized BIM processes guarantee projects are completed within budget and on time.

Read more